mbaun1099 mbaun1099 20-12-2022 Social Studies contestada what is the latest that activity b can start if a lasts 35 days, b lasts 5, days c lasts 6 days, and d lasts 7 days? the process occurs as a (first) b (second) c (third) and d (fourth) question 16 options: 36 40 41 35