Calculate the project earned value (EV).
Type your answer in $M - if the earned value is 10 millions, type 10 as your answer.
b.
Calculate the schedule performance index (SPI).
Type your answer in decimals (round to 1 decimal) - if the SPI is 0.5, type 0.5 (NOT 50%) as your answer.
c.
Calculate the cost performance index (CPI) at the end of month 3.
Type your answer in decimals (round to 2 decimals) - if the CPI is 0.55, type 0.55 (NOT 55%) as your answer.
d.
Use the SPI to estimate the new expected time at completion.
Type your answer in months (round to 1 decimal) - if the SPI is 3.3 months, type 3.3 as your answer.
e.
Use the CPI to estimate the cost at completion at the end of the project (EAC).
Type your answer in $M (round to 1 decimal) - if the CPI is 3.3 millions, type 3.3 as your answer.