Consider the project performance report presented in figure 14.1. What valid conclusion can you draw regarding the project schedule performance as of October 31, 20XX?
Select one:
a. The project is $26,000 behind schedule.
b. The project is 18 days behind schedule.
c. The project is $26,000 ahead of schedule.
d. The project is $18,000 behind schedule.
Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report
(October 31, 20XX)
![Consider the project performance report presented in figure 141 What valid conclusion can you draw regarding the project schedule performance as of October 31 2 class=](https://us-static.z-dn.net/files/d83/9d08a69611fc5305796c55095fa0b54f.png)