The project information for the custom order project of the Air Control Company is presented here. Draw a project network for this project. Compute the early and late activity times and the slack times. identify the critical pathID Activity Predecessor TimeA Order review None 2B Order standard parts A 15C Produce standard parts A 10D Design custom parts A 13E Software development A 18F Manufacture custom hardware C, D 15G Assemble B, F 10H Test E, G 51. Draw a project network for this project. 2. Compute the early and late activity times and the slack times. 3. Identify the critical path. 4. How long will the project take?