given the following project data, draw the project network diagram, identify the critical path, and determine the completion time. assume the project contract states that if the project is not completed by the 14th day, your firm will experience a penalty of $100 per day until the job is completed. determine what, if any, penalty would be incurred. if you need to crash an activity, which activity would you crash first? why? is there a point at which it is no longer cost effective to crash activities?