Mark determined the project he had been working on for two months was ready to close since all of the contracts were completed.Based on the current situation of Mark's project, select the next two steps below that he will perform in the closing process.a.)Refer to governance to determine the documentation left to complete, then obtain feedback to compile lessons learned.b.)Meet with the project sponsor to gain project approval, then meet with the person responsible for taking ownership.c.)Refer to governance to determine the documentation left to complete, then meet with the project sponsor to gain project approval.