the whole process is conducted by three workers in a worker-paced line. the assignment of tasks to workers is the following: worker 1 does activity 1. worker 2 does activities 2 and 3. worker 3 does activities 4 and 5. what is the utilization for the worker with the maximum capacity? (choose the closest answer.)