Most project resources are negotiated by the PM with the functional managers; some areas of negotiation include the
1. Assignment duration
2. Specific individual in the functional area 3. Who selects that person.
4. Under what emergencies, can the functional manager recall team members.
a 1.3, and 4
b 1, 2, and 3
c 2.3, and 4
d 1, 2, 3, and 4​